January
Preparation for the steel enforcements has started.
May
Setting out of form work for the Septic tank
May
Casting of the Septic tank
May
Septic tank Casting is complete
June
They just completed the casting of the six septic tanks.
June
The casting of all six septic tanks is complete.
June
The septic tanks are completed and preparatory work to sink them is ongoing.
August
Overview of wet concrete poured into the formwork to establish the ground beam
August
Installation of service pipe before casting of the ground beams
August
Casting of pile caps
August
Arrange of pile cap reinforcement prior to casting
SEPTEMBER
Compacting of ground floor
SEPTEMBER
Blinding of ground floor
SEPTEMBER
Casting of the ground floor
SEPTEMBER
Formworks for the columns is underway.
SEPTEMBER
Welding of starter bars to columns is complete.
SEPTEMBER
Casting of the columns on the ground floor
SEPTEMBER
Application of bonding chemical and backfilling of ground floor is in progress.
SEPTEMBER
Iron reinforcement works for the pile groups and concrete casting of pile groups is complete.
SEPTEMBER
Ground floor works is ongoing
OCTOBER
Reinforcements of the ground floor columns in progress.
OCTOBER
Formwork of the ground floor columns in progress.
OCTOBER
Casting of ground floor columns is completed.
OCTOBER
Block work to the staircase area is ongoing
OCTOBER
Formwork to the first floor in progress.
OCTOBER
Formwork to the first floor in progress.
NOVEMBER
Formwork is 100% completed on the first floor
NOVEMBER
Polystyrene fittings is 100% Completed on the first floor.
NOVERMBER
Iron reinforcement is completed.
JANUARY
The formwork for the second floor is going on.
JANUARY
Preparation for the steel enforcements has started.
February
Formwork for the second floor is Ongoing
February
Preparation for the steel enforcements has started
February
Formwork for the second floor is 50% completed.
February
Formwork for the Staircase is underway.
March
The Second-floor casting is underway
March
The Second-floor casting is 10% complete
March
The Second-floor casting is ongoing
March
The Second-floor casting in progress
APRIL
3r d-floor formwork in progress.
APRIL
3r d-floor formwork is underway.
APRIL
3r d-floor formwork in progress.
APRIL
3r d-floor formwork in progress.