Follow our progress on Scandic Court II
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/11/sc2223.png?media=1707750034)
EXTERNAL WORK
Electricity and light installation is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/11/hfhg.png?media=1707750034)
AUGUST 2021
Interior work is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/06/scfgf-1.png?media=1707750034)
EXTERNAL WORK
Barb wire and fence installation is completed.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/06/hvgy.png?media=1707750034)
INTERIOR & EXTERNAL WORK
Installation of handrails is completed.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/fbb.jpg?media=1707750034)
INTERIOR & EXTERNAL WORK
Window fabrication and installation is completed.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/pop-feb.jpg?media=1707750034)
INTERIOR WORK
POP ceiling installation is completed – Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/jan-roofing-complete-3-1.jpg?media=1707750034)
INTERIOR WORK
Internal wall screeding and tiles installation – First and second floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/jan-roofing-complete-4-1.jpg?media=1707750034)
EXTERNAL WORK
External wall plastering in progress.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/01/DECEMBER-2020.jpg?media=1707750034)
ROOF FORMWORK
Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/ROOF-BEAM-CASTING-DEC-2-1.jpg?media=1707750034)
ROOF BEAMS CASTING
100% completed – Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/nov-4-1.jpg?media=1707750034)
LINTEL BEAM FORMWORK
Lintel beam formwork – 100% Completed
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/11/pixelss.jpg?media=1707750034)
ROOF BEAM FORMWORK
Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/BLOCK-SETTING-PREP.jpg?media=1707750034)
BLOCK SETTING PREP
Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/sccccc.jpg?media=1707750034)
SLAB CASTING - DAY 2
Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/plastering.jpg?media=1707750034)
OCTOBER 2020
First floor wall plastering / M&E.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/AUGUST-2020-second-floor-block-setting.jpg?media=1707750034)
AUGUST 2020
Second floor slab concrete and block setting.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/06/IMG_8232.jpg?media=1707750034)
JUNE 2020
First Floor Covering.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/05/IMG_7362.jpg?media=1707750034)
MAY 2020
Preparing first floor works, after a Covid-19 pause in works.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/01/sc2november.jpg?media=1707750034)
NOVEMBER 2019
Pile Cup works begin.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2019/09/Pilecupsdone.jpeg?media=1707750034)
SEPTEMBER 2019
Breaking of the pile cups.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2019/08/SC2updateJuly.jpeg?media=1707750034)
JULY 2019
Preparatory work for piling (12m depth)
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2022/07/WhatsApp-Image-2022-07-20-at-6.57.09-PM-1.jpeg?media=1707750034)
June
Blockwork for pile groups was done (11 of 37).
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/11/vnh.png?media=1707750034)
INTERNAL WORK
Interior work is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/11/sc2223r.png?media=1707750034)
JUNE 2021
External work is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/06/vnbx.png?media=1707750034)
EXTERNAL WORK
Ground floor for parking flooring is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/06/scf.png?media=1707750034)
APRIL 2021
Wall painting is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/frbb-1.jpg?media=1707750034)
EXTERNAL WORK
Wall plastering is complete.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/feb1.jpg?media=1707750034)
FEBRUARY 2021
Construction of the gates – Ground floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/jan-roofing-complete-2-1.jpg?media=1707750034)
M&E
M&E installation fittings – Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/jan-roofing-complete-1.jpg?media=1707750034)
JANUARY 2021
THE ROOF IS 100% COMPLETED – Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/dec-carccass-1.jpg?media=1707750034)
ROOF CARCASS
Installation of the roof carcass – Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/ROOF-BEAM-CASTING-DEC-1.jpg?media=1707750034)
DECEMBER 2020
Roof beams casting – Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2021/02/nov-3-1.jpg?media=1707750034)
LINTEL BEAM FORMWORK
Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/11/pixx.jpg?media=1707750034)
NOVEMBER 2020
Lintel Beam Casting – Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/third-floor-column-reinenforcement.jpg?media=1707750034)
COLUMN REINFORCEMENTS
Third Floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/d2.jpg?media=1707750034)
SLAB CASTING
Third floor
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/SEPTEMBER-2020-third-floor-form-work-and-rienforcements.jpg?media=1707750034)
SEPTEMBER 2020
Third floor form-work and reinforcement.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/10/JUNE-2020-first-floor-block-work-setting.jpg?media=1707750034)
JUNE 2020
First floor block setting.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/05/IMG_7216.jpg?media=1707750034)
MAY 2020
Mounting work.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2020/05/IMG_7258.jpg?media=1707750034)
FEBURARY 2020
Ground floor.
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2019/11/3da1937b-a0c6-4e09-8dd3-29153828d7c2.jpg?media=1707750034)
OCTOBER 2019
Pile Column works
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2019/08/sc2piling.jpeg?media=1707750034)
JULY 2019
Piling in process
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2019/08/SC2updateJune.jpeg?media=1707750034)
JUNE 2019
Land filling works
![](https://usercontent.one/wp/www.scandiclion.com/wp-content/uploads/2022/07/WhatsApp-Image-2022-07-18-at-6.49.32-PM.jpeg?media=1707750034)
June
The blinding and block work for a pile group were done (12 of 37)