Follow our progress on Scandic Court II

December 2020
Roof Formwork – Third floor

November 2020
Roof Beam Formwork – Third floor

October 2020
Block Setting Prep – Third floor

October 2020
Third floor Slab casting day 2.

October 2020
First floor wall plastering / M&E.

August 2020
Second floor slab concrete and block setting.

June 2020
First Floor Covering.

May 2020
Preparing first floor works, after a Covid-19 pause in works.

November 2019
Pile Cup works begin.

September 2019
Breaking of the pile cups.

July 2019
Preparatory work for piling (12m depth)

December 2020
Installation of the roof carcass – Third Floor

November 2020
Lintel Beam Casting – Third Floor

October 2020
Column Reinforcements – Third Floor

October 2020
Third floor Slab casting.

September 2020
Third floor form-work and reinforcement.

June 2020
First floor block setting.

May 2020
Mounting work.

February 2020
Ground floor.

October 2019
Pile Column works

July 2019
Piling in process

June 2019
Land filling works