Follow our progress on Scandic Court II

October 2020

Block Setting Prep – Third floor

October 2020

Third floor Slab casting day 2.

October 2020

First floor wall plastering / M&E.

August 2020

Second floor slab concrete and block setting.

June 2020

First Floor Covering.

May 2020

Preparing first floor works, after a Covid-19 pause in works.

November 2019

Pile Cup works begin.

September 2019

Breaking of the pile cups.

July 2019

Preparatory work for piling (12m depth)

October 2020

Column Reinforcements – Third Floor

October 2020

Third floor Slab casting.

September 2020

Third floor form-work and reinforcement.

June 2020

First floor block setting.

May 2020

Mounting work.

February 2020

Ground floor.

October 2019

Pile Column works

July 2019

Piling in process

June 2019

Land filling works